Auburn Junior High School
AUBURN, ALABAMA
The project consisted of a HVAC renovation to existing Auditorium. Commissioning was brought into the project during the construction phase to provide functional performance testing for the existing Building Automation System (BAS). The design called for adding new equipment and modifying an existing 80-ton DX split system. We provided functional performance tests for the existing BAS and worked with the controls contractor to test the BAS. We provided the owner with a report which contained our findings and recommendations for corrections to the BAS.